Trafford Palazzo Manchester
We supplied, manufactured and installed a galvanised steel gantry over 22 metres high on to the roof of Trafford Palazzo for NERF Manchester – all while the building stayed open. Time frame: 2 weeks to supply and install.
🛠 670 assemblies
⚖️ 13.2 tonnes of hot rolled steel & 165 sq.m of steel mesh flooring
📐 21.6m x 7.3m gantry
🚧 2 staircases + 105m of handrail system
🏗 Installed via mobile tower crane (thanks, Hirds!)
Only 2 Taywel team members.
Early last year we were awarded a steel plant deck to be installed on the roof of Trafford Palazzo Manchester. This was a particularly tight time scale and the logistics were complex due to no lay down area on site and the steel gantry needing to be erected 26 meters high on the roof. This was completed without any problems and start to finish the erection took 3 days.